A commercial drawing does not ask what the owner wants. It tells you what is already specified, and the general contractor is usually looking for the lowest number whose scope looks complete. Win that number without the payment terms, the maintenance clause, or a way into the courtyard, and the crew stays busy while the cash sits with someone else.
This is how we estimate, manage, and stay competitive on commercial landscape work. It comes from two conversations on the How to Hardscape Podcast with Jack Hamilton of Hamilton’s Group, who prices commercial work and, close to home, helps manage it. Estimating, Managing, and Being Competitive in Commercial Landscaping with Hamilton’s Group is episode 338. Crossover Episode: Commercial Landscaping with Hamilton’s Group, Paver King, and NDL is episode 297, with Paver King and Chad of Natural Design Landscapes. Dollar figures, sizes, and payment terms below are from those conversations. They are not a rate sheet or a contract clause for your province or state.
A Residential Habit Loses the Bid
On a residential job we often write the scope. On a commercial job the drawings already did. Jack’s picture of acceptance, using a school as the example, is the lowest price whose scope looks complete. A lump sum that says “landscaping, everything on the drawings” fails that test. The estimator across the table cannot see what you included, and can decide you included work that was never yours. His example was a masonry wall in the hundreds of thousands of dollars that happened to sit on a landscape sheet.
Extras follow the same paper. Chad’s point is that a residential client is far easier to collect an extra from. Commercial extras move through a request, a change notice, a price, and an argument about site conditions. Plan to sort it out the way we sometimes do in a backyard, and the general already has a document that says you own it.
Failure mode: you price the package like a patio consult, miss the maintenance clause or the payment holdback, and the number that won cannot cash-flow.
Qualify Your Company First
When someone asks Hamilton’s Group for help, Jack does not start in a bid portal. On episode 338 he walked a short intake and used made-up answers so the questions would show. The dollars in that walkthrough are a teaching prop.
He asks for labor cost without profit and overhead, so the bid sheet has a rate to start from. He asks how many crews and how many people, which is how many jobs you can reliably bid. He asks what you own. A business with just a mini skid steer points them towards courtyards and other tight access. A large contractor may not own a machine that small. They can rent one. You already live in those spaces.
He then asks how far you will travel, what you do best, and what you will do only to support that. In the example, interlock and small walls were the strength. Sod, small plantings, drainage, and light site furnishings could come along. Fences and large trees were a no. The last question is whether commercial requests are already dying on your desk, or whether you have none yet.
That profile is the bid list. A courtyard is hard because the pavers cover the only place you could stack them, and a blower truck for soil or mulch has to show up when the footprint is clear. Jack treats that difficulty as the premium. A large firm can still rent in. Many of them would rather not.
Judgment call: a scope you refused is not always optional. If the form is one lump sum and the fence is inside it, you carry the fence, subcontract it, or you walk. If the fence is its own line, you can leave it off. Including it can make the award easier. Leaving it off also keeps that trade off your crew.
Failure mode: you say you install pavers, then you bid every package in the region and spend the week marking up someone else’s concrete.
Get on a List Before You Hold a Prime Contract
Jack’s first door is people who already know the crew. If you lay pavers well, offer that scope to a larger landscape company as a lump sum. Paver King started there to avoid the invoicing. Two crews worked lump sum or by the hour for a larger contractor. When that company folded, he and Jack kept the client on one messy inherited project, and only then had a stream of invitations. He figured he had priced on the order of 100 to 120 projects between the two companies.
Public bid sites are the door if that network is thin. Do not make a crowded park the first job. See which generals took the plans, price only the package you can build, and send it to each of them. Strangers get thrown out. One estimator who wants a new name is enough. The usual reply is silence.
Price some work you do not love. Landscape is often the last trade still missing a number. Jack’s example was about forty bollards in asphalt, each with a small ring, after someone forgot them. Price it high enough that you would do it, and you get the call when the next package is the one you wanted.
Judgment call: you do not need the prime contract. On one job a larger firm carried a price for about 4,000 square feet of interlock and won. Their edge was equipment and management. The crew’s edge was the pavers. The slice can pay a better percentage than the whole job. Jack will not hold the client’s money. The contractor holds the contract.
Failure mode: you price work you cannot be awarded. Say up front if the crew is not union. Jack put that screen at about half of commercial invitations. One paver subcontract required a COR certification or the bid was discarded. They could price it only because the company carrying them was certified. Read that gate before you measure.
Use the Edge You Already Have
Open tenders are crowded, so the job should use something you already have: trucks, a blower, a hydro-seeder, or speed at one scope. A bid that is mostly another trade is a markup. Jack’s picture was about 70 percent concrete and 30 percent sod, priced by a sod company. Flip the shares and that company is pricing its own work.
Paver King avoids site furniture that can run to about $250,000 with almost no labor and no room to mark it up. You lose if you mark it up, and you still carry the bill if you do not. Concrete does this at a larger scale. A thin markup on a concrete-heavy bid still left them owing the concrete company if the general paid late. Carry it only where the risk is shared.
Cash runs past the 30 days many of us expect. Some generals in the conversation pay in about 30 days, some discount about 3 percent for quick pay, and some take 60, 90, or 180 days. Early-pay discounts, as they described them, sit roughly between 3 and 5 percent depending on the general. Choose cash or points before you chase the discount.
Search every specification for maintenance. Bare mulch can be a return visit, or it can be cutting and fertilizing sod for a warranty Jack described as two years. The bidder who skips the search looks cheap and then owns a maintenance route. Chad described a harsher term: material cost only until that warranty ends, while you finance labor, equipment, and insurance. He has taken it when the company could float the job. A two or three-person crew should not.
Judgment call: they found invasive phragmites in soil stored off site, invisible at bid time. They fixed it because the spec required it and the general was a repeat client. Jack said a one-off might have been pointed at court. That is a relationship call, not a gift you owe every site.
Failure mode: if the sheet shows ten trees and someone says “only price eight,” price ten or get the cut in writing. Time the haul yourself. A softened drive time is a way to drag the number down.
Write the Bid So Another Estimator Can Use It
On episode 338 the bid lives on a calendar, a shared drive, and a Trello board, with your due date the day before the general’s. Jack’s stages are a scope review, takeoffs, a bid sheet, vendor quotes and the wait for them, a note back on which scopes to carry, a line-by-line check, and a quote you approve before it goes out. Some contractors send that quote themselves. He is fine with that.
He starts a new estimator on measurement: a hatched area is sod. Takeoffs are in Bluebeam now, after PlanSwift, including a fill tool for irregular walks. The sheet stays loose because specs and units change from job to job.
Vendor quotes eat the calendar. He buys local, and he stays with your soil yard when that loyalty is real. A wall can wait a week or two on pre-engineered drawings. When a sub walked off an awarded scope, the first time he had seen it, he bought the material and stayed with the contractor’s crew until it was built. He said that one still made money. Do not budget the next walk-off as a plan.
Send separate scopes, not one landscape price. Pavers on one line and planting on another, each one a crew can finish. A general missing pavers elsewhere can lift your line, and can also mix you with a competitor. Be comparable anyway. Put exclusions in writing, including no dust-free cutting and no after-hours work if you did not allow them.
Give the crew quantities they can order: tons of gravel, yards of soil, a rough duration, and the supplier. He will not pretend to see a remote site that morning. He can still say how much gravel. He used 22 tons as that kind of answer. Copy the habit, not the tonnage.
He expects the spread on labor, not on material. Prices land close. A hard look might save a couple of points, and it matters on a big quantity. He used 10,000 yards of imported topsoil as the case. The money is how fast it goes in. He starts from cost per man-hour, puts overhead on the labor, and will not publish either crew’s rate. A long repetitive run gets faster. Two loads and a small sod area do not. Raise production or lower markup until you are in range, and stop where the next cut means you are paying to build the job.
Second place is useful. Jack likes it because first has often made a large mistake. Chad would rather lose wide than win by a hair. They pictured a loss on the order of $200,000 against a win on the order of $2,000. Jack called a healthy pattern, not a quota, first about 20 percent of the time and second about 80. Ask the estimator where you sat. About 10 percent high, or a win by about 4 percent, tells you something. A win about 40 percent under the next number means read the contract again. Those were examples of feedback, not one named result.
Failure mode: the general rewrites the scope and adds work that was never drawn. Sometimes your quote is stapled on, which is the good case. Sometimes they wrote their own, and a gap on the order of $20,000 in his example becomes yours while they keep what they charged upstream. Cross it out. Check the contract total. It is not always your bid.
Stay on the Job After You Win It
There is no clean handoff. Jack reviews the contract, helps build submittals many crews have never assembled, and pulls closeout out of the specifications. He wants the call during the work. A broken walk may not be yours. A demand to move trees may not be in the quote. On episode 338 a site wanted a concrete edge where the drawings called for aluminum edging, about four inches, which is what had been priced. The difference is a change order.
No works once the scope is written. A fifteen-minute unload is help. Replacing sod their machine destroyed is not, if the quote already stated the quantity. Skip time-and-materials for a price they have not seen. The normal path is a form, sometimes a drawing, a quantity such as 100 square meters of sod in his example, your price, and an email to proceed or a short amendment. He used $1,000 only to show a signature line. If the work already happened on a verbal ask, write it down the same day.
Start dates slip. Chad has learned he won when a contract arrived months after the bid. He keeps more than one crew, puts enough people on site to satisfy the general, and moves them. Access vanishes, a trade strikes, or a long job stops because the building is not ready. He used a project on the order of $2 million for that kind of stall. Other crews fill the hole. In one May push, two companies helped lay about 10,000 square feet of pavers in about three days. Chad and a partner can reach six crews without employing all six every week. Three small companies are not one three-person general.
Size is part of the plan. Paver King called about $50,000 to $250,000 or $300,000 a strong range for their people, and was glad, inside a job he put at about $2.4 million, to install about 6,000 square feet of pavers and leave. A longer stay on one site had burned the crew out. Chad prefers about $40,000 to $200,000, hoping to see money inside about 90 days, before extra mobilizations and other trades eat the hours. Those bands are theirs. Do not adopt them because they look round.
A scope duration beats a daily app nobody fills in: five days for this paver area, and on day two you ask if half is down. It fails when pavers and trees have to go in together, because you can no longer tell which scope is slow.
The profitable shops he sees are not hiding a better form. They pay on time, so a supplier will extend credit when a draw is late. They can haul their own material, because removals show up mid-job. More than one machine size means more than one kind of site. One scope others avoid, fences in his example, is an opening if you do it well. And they do not chase ten cents a ton of gravel across five yards. One account gets a harder look on a large order. Open the credit lines before you need them.
How to Start This Week
- Write one page: labor cost without profit and overhead, crews, machines, travel limit, scopes you want, and scopes you will carry only if the form forces them.
- Offer one scope you are fast at, as a lump sum, to five companies that already know the work. Do that before you bid a prime contract.
- On one live tender, search for maintenance, watering, and payment. If labor is held until a warranty ends and you have one crew, decline.
- Price the next package as separate scopes. Write the exclusions, including dust-free cutting and after-hours work when you have not allowed them.
- Ask where you placed on the last three bids. Second is information. A win far under the field is a reason to reread the contract.
- Compare the awarded scope to your quote before you mobilize. Cross out work you did not price. Do not start a change from a verbal ask.
- Stop splitting one material across yards to save a few cents, and apply for a credit account you do not have.
- Skip any package that is mostly another trade, or that needs a union crew or a certification you cannot borrow from the company carrying you.