The patio goes in so the client can sit under the oak. The crew leaves with a full crown, and two to four years later the leaves are smaller, dead wood shows in the top, and the owner asks who dug what. On a hardscape job that shade is often why we were hired. The same work can starve the tree or, if the cut is close and severe, leave it free to tip.

This article comes from Protecting Trees in the Construction Process with Todd Irvine, episode 191 of the How to Hardscape Podcast, published January 30, 2023. Michael Pletz hosted. Todd founded the Toronto company City Forest and is a certified arborist. He has been an arborist for almost 25 years: summer landscaping, an arborist crew, an arboriculture apprenticeship at Humber College, then Bruce Tree, including about ten years consulting on development and permits. City Forest teaches people what is in the yard and how to build without losing the trees they already have.

Every diameter, radius, water volume, and dollar figure below is from that conversation, not the bylaw on the lot in front of you.

The Tree Looks Fine Until Long After You Are Gone

Ten days after the patio, or ten months, Todd often sees nothing wrong. Trees store sugars in the trunk and roots and can live through a winter with no leaves, so the crew is gone before the crown shows the cut. Two to four years later he watches for smaller leaves, fewer leaves, dead wood in the top, and sometimes death. A young tree can recover. A mature trunk, which he put at potentially a hundred, two hundred, or three hundred years, is much less likely to. Severe root loss on a tree that old, he said, is closer to surgery on an old person.

A large tree that cannot pull enough water dies from the tips. He described a tree as a pump. Water moves from the roots into the crown, and tiny openings in the leaves let it out as vapor when the leaves heat up, which he called evapotranspiration. He put one tree’s daily draw at about 450 to 500 liters, which he also called about 150 gallons. Those two figures do not convert into each other. They are his picture of the volume, not a reading off your tree. Cut the absorbing roots, or seal the soil so rain never reaches them, and the top thins.

The other outcome is a tip-over, when excavation is severe and very close to the trunk. In workshops for landscapers, designers, and landscape architects, one slide is a Norway maple through the front of a house. Installers in the room notice the new retaining wall. Tiebacks meant digging past the wall and cutting the roots that held the tree. Roots pull water and they anchor. About two feet of soil on that system, he said, is what keeps a tree up in winds around 100 kilometers an hour.

If the tree dies or comes down, a consulting arborist and lawyers work backward from photos. A mini excavator, or two feet of soil gone under the canopy, is enough to tie the damage to the dig. The company that opened the ground is in that file.

Most of the Roots You Can Hit Sit Near the Surface

People draw a tree from the ground up. Todd’s correction is that a large share of it is below grade. He said almost 45 percent, give or take, and also 40 percent or more. Use that as the range he offered.

The roots a patio hits are shallow. He said the vast majority sit in the top two feet of soil, and the fine absorbing roots sit in the top foot, because that is where rain lands. He calls the spread a mat: woody roots a bucket hits, and fine roots waiting on a short storm. His picture was a hot August, three weeks dry, then twenty minutes of rain.

Roots also reach past the drip line, the edge of the leaves, so rain outside the crown is not wasted. He said they can run about twice the height of the tree. A 50-foot tree, in his example, might send roots 100 feet out. He also called that root system 200 feet in every direction. Do not tape either number across a city lot. That picture is a farm oak in an open field, already scarred by the plow. A yard boxed in by houses is harder. One corner of a huge field root system may not matter. The same dig, where every root is trapped in the backyard, is a much bigger share of what the tree has left.

Map the Protection Zone Before Anyone Digs

Start on paper. Map the yard, design it, and inventory the trees. Some are already dying, and removal belongs in the scope. Others are the client’s tree, the neighbor’s, or a city tree, and those set the distance before the layout gets precious.

Rules are local. In much of Canada, he said, tree protection bylaws restrict both cutting a tree and damaging one, or working around it, without permission, on city land and on private land. For U.S. listeners he said rules like this are showing up, and a city tree on the road allowance, the strip the city owns across the front, is already in play. He did not say every private tree in the United States is covered the way he described private trees in Canada. Read the table on the drawings.

His Toronto-area pattern, which he also tied to Brampton, Oakville, and Vaughan, should stay labeled as his account. A trunk of about 30 centimeters, about a foot, needs a 2.4-meter protection radius. He called that about five meters across, and later about eight feet of radius. A trunk of about 100 centimeters needs a six-meter radius, about 12 meters across, which can be a whole backyard. He told people to search for a tree protection zone table: 2.4 meters at 30 centimeters, then about 60 centimeters more radius, about two feet, for each extra 10 centimeters of trunk. Those two examples do not multiply into one formula, so open the local table. The size that triggers protection, he said, is often about 20 centimeters, roughly nine or ten inches, or about 30 centimeters, depending on the town.

You are not supposed to work inside that zone until the work is planned, usually with an arborist report and a tree protection plan, and permission is in hand.

He told a front-yard job that shows who pays. Ian Bruce, the arborist Todd worked for, came in after a contractor built a parking pad and driveway with no permit and no arborist, on the city road allowance, and cut the roots of a large city silver maple. The city hired Ian as a third party. Too many roots were gone and the tree was likely to fall. The city priced the tree, by a method Todd did not name, at $25,000, added fines, and required a replacement. Todd remembered the driveway as about a $25,000 job and the fine as something that could land around $40,000, then a claim from the homeowner, because the city and the neighbor bill the client first. He called it one case in a hundred, and said that one case can bankrupt a company. Those dollars are his memory of that file, not a price list.

Cut a Root the Way You Would Prune a Branch

A bucket does not excavate a root mat nicely. Stay out of the zone when the design can live somewhere else. If you must cut, dig by hand or excavate carefully, ideally with an arborist there, and cut clean on purpose.

You would not prune a limb with an excavator tooth, because the tear runs into wood you meant to keep. Pounding a root does the same underground. It shakes back to the trunk, snaps side roots, and a rip pulls the break past the hole. A clean cut, only on the line the layout needs, is the wound he will stand behind.

Machines also compact ground you never meant to pave. Compaction under a base keeps pavers from settling in waves. The same compaction in a bed squeezes out pore space, blocks water, drops oxygen, and kills roots that grow by pushing through loose soil. Parking trucks in the shade under the canopy for a week, which he sees constantly, can do that in ground you never excavated. If the backyard is the only way in, keep the hole small and the machines on the work.

To see the roots, he uses an air spade: high-pressure air, a rented compressor, soil blown off without a cut. Hydrovac can work, but the water jet can damage roots, the truck is large, and it costs more. The air also finds a cord buried out to a shed. On a company with several crews, one person can earn the International Society of Arboriculture certified arborist credential he described, by showing landscape experience and work with trees, then write the report and run the careful dig. You do not need a decade of climbing first. Clients who care about the tree pay for that, and they remember the quotes that never mentioned the neighbor’s oak.

Bases That Still Let the Tree Drink

The build he pushed back on is the automatic one: excavate about a foot, compact, place on the order of ten inches of limestone screenings, compact again, and lock pavers tight. That is a real patio. It is a hard thing to put on a living root mat.

Limestone screenings are common where he works because Ontario has the quarries. Compacted, fines and all, he said that layer is about as hard as concrete, not the porous base the name suggests, and the fines are very high in pH. He has seen trees yellow after a yard was buried in screenings. A tight surface with almost no joint then stops rain from reaching roots you may not have cut, and the tree he described drawing on the order of 150 gallons or 500 liters a day has nothing left to draw.

A fire lane that has to carry a truck is not the place to experiment. A walk to a shed is. Driveway depth is not automatically the depth under a mature tree.

On his own yard he set flagstone on HPB, high-performance bedding, which he called self-leveling rather than compacted screenings. Soil sloped away from the house, HPB went about ten inches deep in places because of that slope, and the stone was dry-laid, no mortar, joints under about an inch. He said it had not shifted on that Ontario patio. On a master’s field course in forest conservation he watched a town in Spain lift cobbles about two hundred years old, finish sewer work, and set the same stones back. Dry-laid work can come up again. Mortar and heavy compaction do not have to be the default beside a tree.

When the patio has to come close, Michael described a permeable joint and synthetic panels in place of a deep base: about an inch of HPB, a polypropylene foam panel about three-quarters of an inch thick, pieces about two by three feet that lock, then the pavers. The dig stays shallow and, as he described those panels, water can pass. Todd’s point was load. Locked units spread weight instead of point-loading the soil. He has used plastic cells he called GeoBlock, about two or three inches deep and filled with aggregate, including a church lawn turned to parking under large oaks. They still dug, but less, and the grid spread the load. Campuses use the same idea where lawn has to carry a fire truck.

Will roots chase water through an open base and wreck the interlock? He is not worried about the fine ones. They want water, but also nutrients and soil, and he has not seen them fill gravel. The root that heaves a patio is the thick one you bridged. It fattens and lifts the surface, and the biggest of those sit near the trunk. Around Toronto he does not see much of that. The season is shorter and growth is slower. Trade magazines from hotter places are full of lifted sidewalks, and a large ficus, maple, or oak in a climate like California, built tight to the trunk, will move the work. Stay off those big roots.

How Close the Patio Can Come

There is no single setback. A young tree shipped as a root ball has already lost most of its roots and can still grow, so you can work closer. A Japanese maple or another small ornamental can still be wrecked, but his comfort there was within about a meter, sometimes less.

A mature trunk changes it. About 40 centimeters or more, over about a foot: inside two or three meters, cutting roots more than about a foot deep, is a tip-over risk in his words, even on one side. A ring of excavation is much more likely to kill the tree than one corner. Treat the roots as a pie and take a slice, not the whole pie. Pavers and a compactor run into the root flare finish a tree. Asphalt in the flare cooks roots that need to stay cool, on a system you have already cut and dried out.

He would rather stay outside about two meters of a mature trunk. Closer than that, only on a short arc, and change the section: a panel, a shallow base, a deck, pea gravel, or stone on grade or on a light base. Say it in the proposal. This sits nearly on grade because of the tree, and if it heaves in about five years we reset it for a small fee. Clients who wanted the oak usually take that over a poured walk that cannot move for anything underground.

Or go up instead of down. A step about ten feet out, another about ten feet later, and the path raised between them so you never open the soil.

Say it on the first visit. In his own quoting, Todd hears that three other prices never mentioned the neighbor’s oak. Some clients have no trees and do not care. The ones who do often have the old canopy, and those are the jobs worth doing carefully. Trees add value. Naming the roots, the likely permit, and a build that leaves the crown standing is how you separate the bid from a crew that comes through like a bull in a china shop.